|
Facility
Commissioning Group is a member of the
U.S. Green Building Council and our
commissioning process adheres to the
requirements of the 2009 Leadership in Energy
and Environmental Design (LEED)
Green Building Rating System - New
Construction
Version 3.0 pertaining
specifically to Energy and Atmosphere
(EA) Prerequisite 1: Fundamental
Commissioning of Building Systems and
EA Credit 3: Enhanced Commissioning.
Benefits of commissioning for LEED
include reduced energy use, lower
operating costs, reduced contractor
callbacks, better building
documentation, improved occupant
productivity, and verification that the
systems perform in accordance with the
owner's project requirements.
LEED-NC Version 3.0 section EA
Prerequisite 1: Fundamental
Commissioning of Building Energy Systems
Intent:
Verify that the building's energy
related systems are installed,
calibrated, and perform
according to the owner's project
requirements, basis of
design and construction documents.
Requirements:
Designate an individual as the
Commissioning Authority (CxA) to
lead, review, and oversee
the completion of the commissioning
process activities.
a) The CxA shall have documented
commissioning authority
experience in at least
two building projects.
b) The individual serving
as the CxA shall be independent of the
project's design and
construction management, though they may
be employees of the firms
providing those services. The CxA
may
be a qualified employee
or consultant of the Owner.
c) The CxA shall report
results, findings and recommendations
directly to the Owner.
d) For projects smaller
than 50,000 square feet, the CxA may
include qualified persons
on the design or construction teams who
have the required
experience.
Owner shall document the Owner's Project
Requirements (OPR).
Design team shall develop
the Basis of Design (BOD). The CxA shall
review these documents
for clarity and completeness. Owner and
design team shall be
responsible for updates to their
respective
documents.
Develop and incorporate commissioning
requirements into the
construction documents.
Develop and implement a commissioning
plan.
Verify the installation and performance
of the system to be
commissioned.
Complete a summary commissioning report.
LEED-NC Version 3.0 section EA Credit
3: Enhanced Commissioning
Intent:
Begin the commissioning process
early during the design process
and execute additional
activities after systems performance
verification is
completed.
Requirements:
Prior to start of construction
documents phase, designate an
independent Commissioning
Authority (CxA) to lead, review, and
oversee the completion of
all commissioning process activities.
The
CxA shall, at a minimum,
perform Tasks 2, 3 and 6. Other team
members may perform Tasks
4 and 5.
a) The CxA shall have documented
commissioning authority
experience in at least
two building projects.
b) The individual serving as the CxA
shall be:
i. independent of the work
of design and construction;
ii. not an employee of the design
firm, though they may be
contracted through them;
iii. not an employee of, or contracted
through, a contractor, or
construction manager holding
construction contracts; and
iv. (can be) a qualified employee or
consultant of the Owner.
The CxA shall conduct, at a minimum,
one commissioning design
review of the Owner's
Project Requirements (OPR), Basis of
Design
(BOD), and design
documents prior to mid-construction
documents
phase and back-check
review comments in the subsequent design
submission.
The CxA shall review contractor
submittals applicable to systems
being commissioned for
compliance with the OPR and BOD.
This
review shall be
concurrent with A/E reviews and
submitted to the
design team and the
Owner.
Develop a systems manual that
provides future operating staff the
information needed to
understand and optimally operate the
commissioned systems.
Verify that the requirements for
training operating personnel and
building occupants are
completed.
Assure the involvement by the CxA in
reviewing building operation
within 10 months after
substantial completion with O&M staff
and
occupants. Include
a plan for resolution of outstanding
commissioning-related
issues.
|